We had a task force meeting today at Arbor Heights. There were a LOT of folks in attendance. First up was the report from the company which has been testing the soil around the affected classrooms. They determined the cause of water under classrooms was not due to ground water - but is most likely due to leaks in the roof drainage system. They presented a diagnostic and repair scenario.

There has been a lot of progress on the univent heater installation. The new air intake system should make a positive difference in air quality.

Big questions about creating a negative air space under all the classrooms to stop possible bad air from entering classrooms from the crawl spaces below. Testing of exhaust fans will happen Monday.

It was a very intense meeting - lots to report on, and much discussion about our school's healthy future. I continue to be optimistic - Mark